How much steel quantity required for 1 cubic meter concrete

Steel is the most important material for any structural construction. So we are going to calculate how much steel quantity required for 1 cubic meter concrete. Only Concrete not used in any structural construction because the compressive strength of concrete is very good. But the tensile strength of concrete is very less and steel used in concrete to increase the tensile strength of concrete.

Steel used in concrete in the form of steel bar. Steel bar is also commonly know as rebar, rod, or reinforcement bar.

You cannot even imagine the construction of a structural member like column, beam, slab and footing without steel bar. Because even if you get these structures constructed without steel, then they are of no use, and such a structure can cause loss of life anytime.

How To calculate Quantity of steel in 1m3 concrete
How To calculate Quantity of steel in 1m3 concrete

How to Calculate Quantity of Steel in Footing, column, slab, and beam

Since columns, beams, slabs, and footing are the supporting structures of any building. Therefore steel should be used in all these structures along with concrete. Because all these structures handle the weight of the building, and through them, the entire weight of the building is transferred to the ground.

Steel must be used in columns, slabs, beams, and footings and the same is determined by the Thumb rule. So in this article, we will learn how to calculate steel quantity in Slab/ footing/ column/ beam.

As a thumb rule, different amounts of steel required for columns, slabs, beams, and footings.

  • According to the thumb rule, 2.5% steel is required for the total weight of the concrete for the column.
  • According to the thumb rule, 1% steel is required for the total weight of the concrete for the slab.
  • According to the thumb rule, 0.5% steel is required for the total weight of the concrete for the footing.
  • According to the thumb rule, 2% steel is required for the total weight of the concrete for the beam.

How to calculate the quantity of steel in column

How much steel required for the column: To calculate the amount of steel in the column, we need to know the length, width, and thickness of the column. And we should know the density of steel.

The density of Steel = 7850 kg/m3.

According to the thumb rule, 2.5% steel required for the total weight of the concrete for the column.

Assume the length of the column = 5 m.

width of the column = 0.609 m.

The thickness of the column = 0.609 m.

Now, first of all, we have to calculate the volume of concrete = length × width × thickness.
= 5 × 0.609 × 0.609 = 1.854 m3.

Required steel quantity = steel quantity percentage × density of steel × volume of concrete

= (2.5/100) × 7850 × 1.854
= 363.847 kg.

How to calculate the quantity of steel in Slab

Steel calculation for the slab: To calculate the amount of steel in the slab, we need to know the length, width, and thickness of the column. And we should know the density of steel.

The density of Steel = 7850 kg/m3.

According to the thumb rule, 1% steel required for the total weight of the concrete for the slab.

Assume the length of the slab = 8 m.

width of the slab = 5 m.

The thickness of the slab = 0.10 m.

Now, first of all, we have to calculate the volume of concrete = length × width × thickness.
= 8 × 5 × 0.10 = 4 m3.

Steel quantity for slab = steel quantity percentage × density of steel × volume of concrete

= (1/100) × 7850 × 4
= 314 kg.

How to calculate the quantity of steel in footing

Steel calculation for the footing: To calculate the amount of steel in the footing, we need to know the length, width, and thickness of the column. And we should know the density of steel.

The density of Steel = 7850 kg/m3.

According to the thumb rule, 0.5% steel required for the total weight of the concrete for the slab.

Assume the length of the footig = 2 m.

width of the footing = 2 m.

The thickness of the footing = 0.30 m.

Now, first of all, we have to calculate the volume of concrete = length × width × thickness.
= 2 × 2 × 0.30 = 1.2 m3.

Steel quantity for footing = steel quantity percentage × density of steel × volume of concrete

= (0.5/100) × 7850 × 1.2
= 47.1 kg.

How to calculate the quantity of steel in beam

Steel calculation for the beam: To calculate the amount of steel in the beam, we need to know the length, width, and thickness of the column. And we should know the density of steel.

The density of Steel = 7850 kg/m3.

According to the thumb rule, 2% steel required for the total weight of the concrete for the slab.

Assume the length of the beam = 5 m.

width of the beam = 0.30m.

The thickness of the beam = 0.30 m.

Now, first of all, we have to calculate the volume of concrete = length × width × thickness.
= 5 × 0.30 × 0.30 = 0.45 m3.

Steel quantity for beam = steel quantity percentage × density of steel × volume of concrete

= (2/100) × 7850 × 0.45
= 70.65 kg.

Must Read Article:

How to Calculate Quantity of Steel for Footing, column, slab, and beam in 1m3 concrete

how much steel quantity required for column in 1m3 concrete

volume of concrete is = 1m3.

According to the thumb rule, 2.5% steel required for the total weight of the concrete for the column.

density of steel = 7850 kg/m3.

The Steel quantity for column in 1m3 concrete = percentage of steel × steel density × volume of concrete.

= (2.5/100) × 7850 × 1
= 0.025 × 7850 × 1 = 196.25 kg.

how much steel quantity required for slab in 1m3 concrete

volume of concrete is = 1m3.

According to the thumb rule, 1% steel required for the total weight of the concrete for the slab.

density of steel = 7850 kg/m3.

The Steel quantity for salb in 1m3 concrete = percentage of steel × steel density × volume of concrete.

= (1/100) × 7850 × 1
= 0.01 × 7850 × 1 = 78.5 kg.

how much steel quantity required for 1m3 concrete footing

volume of concrete is = 1m3.

0.5% steel required for the total weight of the concrete for the footing According to the thumb rule.

the density of steel = 7850 kg/m3.

The Steel quantity for footing in 1m3 concrete = percentage of steel × steel density × volume of concrete.

= (0.5/100) × 7850 × 1
= 0.005 × 7850 × 1 = 39.25 kg.

how much steel quantity required for 1m3 concrete beam

volume of concrete is = 1m3.

2% steel required for the total weight of the concrete for the beam according to thumb rule

The density of steel = 7850 kg/m3.

The Steel quantity for beam in 1m3 concrete = percentage of steel × steel density × volume of concrete.

= (2/100) × 7850 × 1
= 0.02 × 7850 × 1 = 157 kg.

Conclusion:

In this article, we discussed how much steel Quantity required for 1 cubic meter concrete Footing, column, slab, and beam and we have calculated How much Quantity of Steel required for Footing, column, slab, and beam in 1m3 concrete.

1 thought on “How much steel quantity required for 1 cubic meter concrete”

  1. Please calculate total material for construction of linter structure of
    1200 Sq Ft in hill station Murree without footing which is already condtrcted

    Reply

Leave a Comment